Field Development Plan — Big Foot

Summary

A dry-tree tension-leg development with reported first oil in November 2018.

Historical source snapshot, not a current operating-status assertion or a sanctioned engineering design. Missing inputs are preserved as unknown.

Revision history

RevisionDateWhat changed and why
Initial2026-10-19 Documented the reported development concept and evidence gaps to provide a field-level portfolio reference.
12026-10-20Formatted whole-number inputs without decimal padding for readability.

Engineering rationale

The reported arrangement combines drilling, workover and production on an extended tension-leg platform. Dry trees and top-tensioned risers provide direct well access from the facility. This is a description of the reported selection, not a fresh comparison of host concepts.

Field parameters

InputValueSource and scope
Operator at source dateChevronS1: Operator identified in the project overview.
Reported development concepttlpS1: Floating, drilling and production facility section identifies the extended tension-leg platform and dry trees.
HostExtended tension-leg drilling and production platformS1: Floating, drilling and production facility section; no vessel identity is needed.
Water depth (m)UnknownRequired input; not established by the cited evidence.
Wells (scope stated below)UnknownRequired input; not established by the cited evidence.
Designed peak capacity (boe/d)UnknownRequired input; not established by the cited evidence.
Reported oil capacity (bbl/d; not a boe/d plateau)75000S1: Facility section reports 75,000 barrels of oil per day; gas capacity is separate. This is facility capacity, not a boe/d production plateau.
Recoverable resources (MMboe)UnknownRequired input; not established by the cited evidence.
Actual first-oil year2018S1: Overview reports the field came on stream in November 2018.

Architecture

Dry-tree wellheads on the platform connect through top-tensioned risers; processed fluids leave through export infrastructure. No subsea wet-tree layout is implied.

Well coordinates, manifold counts and interconnection lengths are required inputs for a detailed layout. Layout: NOT_EVALUATED; no assumed geometry is drawn.

Recommended concept shortlist

NOT_EVALUATED. The reported concept is documented above; a comparative ranking requires sourced screening limits and criteria weights.

Economics and execution

NOT_EVALUATED. No cost or investment return is inferred from facility capacity. Required inputs include scope-matched capital cost, operating cost, production profile, prices, discount rate and schedule. Equipment qualification and installation feasibility also require project-specific design evidence.

Known limits and way forward

The source gives inconsistent water-depth figures, so metric water depth is unknown here. Initial producer and injector plans are not an installed-well inventory; well count remains null. Obtain a dated well inventory and facility design basis before drawing a detailed layout or evaluating costs.